Progress claim calculator
Invoice your project as it progresses: claim amount, the 5% retention, VAT and net payable, all worked out live. Free, no sign-up.
Your job site
Your situation
Retention held
165,00 €
Left to invoice
12 000,00 €
The retention (5% max) is released a year after handover, unless snags remain, or can be replaced by a bank guarantee.
How it works
Describe the contract
Total contract value and the percentage completed to date.
Deduct what is already invoiced
The tool works out the claim to invoice, excluding work already settled.
Apply the retention
Retention, VAT and net payable, ready for your invoice.
Frequently asked questions
How do you work out a progress claim?
You apply the percentage completed to the contract value to get the work done, then subtract what earlier claims already invoiced. The difference is the amount of this claim.
What is the 5% retention?
The client may hold back up to 5% of the works to guarantee proper completion (French Act no. 71-584). It is released a year after handover, unless snags remain, or can be replaced by a bank guarantee.
Is the retention worked out on the net or the gross amount?
The retention applies to the gross amount of each progress claim or deposit. It is deducted from what is payable, not from the VAT owed.
Other free tools
All the toolsInvoice generator
Create a professional, compliant invoice and download it as a PDF. Legal wording included.
Ouvrir Compliance scoreInvoice wording checker
Check live that your invoice carries the wording French law requires.